2011 Scoping Study


The February 2011 Scoping Study was based on the revised JORC Inferred Resource for Mount Peake published in 2010 of 139.1Mt @ 0.29% V2O5, 5.34% TiO2 and 23.66% Fe. In addition to this resource, TNG has published an Exploration
Target1 of 500-700Mt grading 0.2-0.4% V2O5 and 25-35% Fe.
Click here to view the full Snowdens Scoping Study on the Mount Peake Project.
The Scoping Study was commissioned based on a conventional open pit mining operation processing 5Mtpa, which is
significantly higher than the original 2Mtpa processing rate contemplated in the original 2009 Scoping Study. Initial
optimization work by Snowden indicates that the economics of the Project is sensitive to commodity pricing, exchange
rates and processing rates.
Open pit optimizations were performed based on a 5Mtpa operation, with production commencing at 2Mtpa and ramping
up after three years to the long-term processing rate of 5Mtpa. The study was based on a total identified mining inventory
of 106Mt @ 0.33% V2O5, 6.04% TiO2 and 25.39% Fe with ore processed initially through a 2Mtpa plant designed to
produce vanadium pentoxide (V2O5), titanium dioxide (TiO2) and iron oxide (Fe2O3) concentrate utilizing the newly
developed hydrometallurgical process.
The initial plant total CAPEX2 included in the modeling has been estimated by METS to be $370M, with a +- 35%
accuracy. This would be expanded to 5Mtpa capacity at an additional estimated total CAPEX of $307M after three years,
partially funded by cash flow.
Test work carried out by TNG and METS has shown that the magnetic concentrate that would be produced from Mount
Peake material is amenable to hydrometallurgical processing, resulting in high recoveries of vanadium (90%) and iron
(58%) in the acid leaching. METS advise that recoveries may continue to improve with further optimization work currently
underway.
Concentrate product would be trucked to a conceptual railhead near Barrow Creek on the Alice Springs-to-Darwin railway
line (approximately 70km) and then railed to Darwin (approximately 1,180km) for shipping.
The key findings of the Scoping Study are as follows:
| 23.63 years |
| 5 Mt /annum |
| 107.1 million tonnes |
| 0.33% V2O5, 25.39% Fe, 6.04% TiO2 |
| 349kt V2O5, 27,182kt Fe, 6,463kt TiO2 |
| $46.6/tonne |
| $370.3M (for Stage 1 – 2Mtpa) |
| $307.6M (for Stage 2 – 5Mtpa) | |
| $148.37M / annum |
Key assumptions of the Scoping Study included:
| |
| |
| |
| |
| |
| |
|
To view the announcement regarding the recent Scoping Study results, please click here.
Area |
A$ Million |
Direct cost |
|
Crushing |
13.8 |
Beneficiation |
2.3 |
Leaching and CCD |
32.5 |
Metal extraction and purification |
24.1 |
Vanadium precipitation, drying and packing |
12.3 |
Acid regeneration and precipitation of iron oxide |
131.2 |
Reagent and utilities |
26.9 |
Direct cost sub-total |
243.0 |
Indirect cost |
|
Field indirects |
29.2 |
EPCM |
36.4 |
Vendor reps |
1.8 |
Capital spares |
6.0 |
Commissioning spares |
1.8 |
Insurance |
3.7 |
Indirect cost sub-total |
79.0 |
Total cost |
|
Contingency |
48.3 |
Grand total |
370.3 |
Area |
A$ Million |
Direct cost |
|
Crushing |
25.2 |
Beneficiation |
4.2 |
Leaching and CCD |
59.4 |
Metal extraction and purification |
44.2 |
Vanadium precipitation, drying and packing |
22.5 |
Acid regeneration and precipitation of iron oxide |
240.1 |
Reagent and utilities |
49.2 |
Direct cost sub-total |
444.8 |
Indirect cost |
|
Field indirects |
53.4 |
EPCM |
66.7 |
Vendor reps |
3.3 |
Capital spares |
11.2 |
Commissioning spares |
3.3 |
Insurance |
6.7 |
Indirect cost sub-total |
144.6 |
Total cost |
|
Contingency |
88.4 |
Grand total |
677.8 |